Feasibility report and DPR for installation of roof top grid connected power

04 Feb 2017 05 Feb 2018

Under the project, 44 buildings of GHMC was surveyed for feasibility for developing rooftop solar PV projects. The buildings are distributed across Hyderabad in five zones which are North Zone 7 buildings; East Zone 16 buildings; West Zone  4 buildings; South Zone  9 buildings; Central Zone  8 buildings. The buildings include hospitals, community halls, office buildings, parks, stadiums, slaughter houses etc. with roof area varying from 600 sq. m to 13,000 sq. m. In order to complete this task, TERI would form an expert team which include technical, financial, and regulatory and policy experts who would be working concurrently on the project. The team so formed would work in synchronization with the project monitoring team from GHMC. It would also submit fortnight report on the status of the project to project monitoring team.